General Figures (approximations)

Statistical data Federation RS BiH
Parcels/plots     10 million
Inhabitants 4.5 million

Political  municipalities

85 63 148
Right holders  (ownership / possession / occupancy rights ) 2.0 million
Land and objects  1.61 million

Apartments with occupancy rights 

0.26 million

Other rights (usufructs, mortgage, rights-of-way)

0.13 million

 

Estimation of Total Implementation Costs (KM)

New Survey for 8-10% of territory of BiH

65

Updating of Real Property Cadastre throughout BiH

 

     Preparatory steps (Numerical markings of buildings, lists etc.)

44[1] 

     Public disclosure process

175.3 

     Updating the survey and related costs

79.2 

    Training

0.4

    Data Entry

8.8

    Survey Inspection

0.6

Digitalisation of Plans3

100.0

Technological Network (See Annexes IV – VI)

24 

 TOTAL:

 497.3 million

 Estimation of Maintenance Costs (per year)

Personnel

14.4 million

Equipment and materials

7.2 million

 Breakdown of Costs:

I. Cost estimation for finalising the new survey for the remaining 8-10% of the territory

Since 1951, 92% of parcels in BiH have been numerically surveyed (new survey), and the costs for the remaining 8% are estimated at 65 million KM.

 

BiH

8-10% of parcels needs new survey

Per parcel

Costs

Parcels

10 million

0.8 million

KM 81

65[2] 

II. Preparatory steps for Public Disclosure

Out of 3165 cadastre municipalities, the real property cadastre has been implemented in about 600,[3] representing approximately 1,200,000 plots. Therefore, the number of plots which need to be part of the preparatory steps and the disclosure process is about 8,800,000.

Parcels Per parcel Costs
8,800,000 5 KM 44 million KM

 

III. Cost estimation for Public Disclosure

Costs / commission

cost / month (KM)

Cost / year (KM)

1 Lawyer = President

2,000

24,000

1 Geodetic Surveyor

1,700

20,400

1 Citizen

1,000

12,000

Admin /tech./ overhead

7,200

86,400

Total

11,900

142,800

All salary costs are indicated in gross.

Looking at past experience in establishing the real property cadastre (Visoko, Banja Luka, Konjic…)[4], and looking at what public disclosure activities need to be accomplished, one can state the following:

  • On the basis of 6 decisions on private property per day, and 220 working days per year, annually, a commission can issue about 1,320 decisions per year. Each decision will relate on average to 6 parcels, therefore a commission will deal with about 7920 parcels per year. In addition, the 260,000 apartments with occupancy rights will be privatised, and will need to be registered for the first time. About 10 decisions on registration of privatised apartments could occur per day, producing 2200 decisions per year.  

  • In order to deal with all 8,800,000 outstanding parcels, and all 260,000 apartments with occupancy rights, the total cost for commissions would be 175,300,000 KM.

 

  Decisions per day

Parcels per decision

Decisions per year

Parcels decided per year

Price per parcel and  occupancy right

Cost of Commissions

(Million KM)

Private Property

6

6

1320

7920

18

158.4

Occupancy Rights

10

-

2200

-

65

16,9

TOTAL

175.3

 

IV. Other costs associated with the establishment of the Real Property Cadastre

In addition to the costs related to the public disclosure process, an additional 9 KM per parcel would need to be allocated for updating the survey if and where required (these costs would be higher in urban centres, less in rural areas), adding an additional 79.2 million to the costs for updating of the Real Property Cadastre.

Other related costs:

Training:

400,000

Data Entry

8.800.000

Survey Inspection

600,000

Digitalisation of Plans[5]

100.000.000

 

V. RPC- Maintenance costs

 

Personnel

RPC-offices

Persons/office

Employed (BiH)

costs / persons month (KM)°

costs / year (KM)

150

8

1,200

1,000

14,400,000

 

Equipment and materials

 

10,000,00

Total

24,400,000

 



Figures based on estimations of researchers.

[1] Estimated figures based on interviews with competent persons in cadastre offices and experience of competent staff within the CRPC. 

[2] Estimated by Karabeg Dedo, Federal Geodetic Administration, on the basis of previous survey costs.

[3] According to data provided by the Republic Geodetic Administration for the seminar “Reprivatisation, Establishment of Real Property Cadastre and the Resolution of Property-Legal Relations” in Sarajevo, November 1991.

[4] For example, the Visoko Commission would issue 6 decisions per day; Banja Luka 5.5 per day; Konjic (pre-war) 7-8 per day; (post-war) 3-5 per day.

[5] Digitalisation costs are based on costs in Austria and costs of the Visoko RPC office. Digitalisation costs per plot (including connection to GIS) would cost 10 KM per plot. For all 10,000.000 plots, (given that very minimal digitalisation has occurred to date – only parts of Visoko municipality and parts of municipalities within the RS), costs are estimated at 100 million KM.

° Salaries are in gross.

 

top l back to World Bank Study

 

K.U.Leuven - Claim Copyright © Katholieke Universiteit Leuven | Reactions as to the content: Johan Verlinden
Production: Johan Verlinden | Most recent update: 16-05-2012 | Disclaimer
URL: http://www.law.kuleuven.be